You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register
Get Started with Redwood for Oracle Cloud HCM   Begin Now
To ensure that questions get required attention from community members and are NOT left unanswered, it’s important for the author to indicate (by selecting “Yes” or “No” when prompted) whether the question was answered. (newly added) Please note that it is also important to respond to EACH comment your question receives. Your Yes or No response ensures an accurate status for your question.

For more information, please refer to this announcement explaining best practices for getting answers to questions.

Issue with Proration based on actual number of working days in year i.e. 260

edited Feb 9, 2022 9:59AM in Payroll and Global Payroll Interface (GPI) 1 comment

Summary:

Issue with Proration based on actual number of working days in year i.e. 260

Content (required):

Hi All,

We are having an annual salary basis and want to prorate earnings elements by actual working days i.e. 52*5 = 260

Consider an employee having annual sal = 30000 and hired on 12-Dec-21, the actual working days in Dec would be 15. So the Dec-21 earning should be 30000/260 * 15 = 1730.77

But it is getting calculated as 30000/260 * 14 = 1615.38 i.e. system is considering one working day less, 14 instead of 15.

Anyone faced similar issue or any advise to achieve this would be great help.