Unable to issue partial quantity of component to maintenance work orders
Summary:
Unable to issue partial quantity of component to maintenance work order after the work order pick line is split and confirmed for partial quantity
Content (required):
Hi,
For our client Ma'aden we have the following requirement -
- Work order created with required quantity of component item (supply type push) as 13
- User reserved the material.
- User ran Release and Pick Material
- Pick slip generated for all 13 quantities
- Business requirement is they don't want all the required quantity at one go.
- Hence the warehouse user during pick confirmation, split the lines and confirmed only 6 quantities.
- Now user needs to manually issue the 6 picked component quantities to work order (plant parameter we have disabled the option issue push components on picking)