GOP pegging not showing details of component
Summary:
We are using CTP . We have enabled Check ATP and ATP components and set as Material and Resource for Make parts and for Buy components these are set as Material and None respectively. When we do a GOP inquiry we see that the pegging tree shows the top level assembly followed by the resources(enabled for ctp) but the pegging does not show the component details below the resources.
Content (required):
Please see example below. 17651645-001 is top level item . You can see details for it and then the resources below it but this top level item has a component under it which is not showing in this tree below. We have run planning collections followed by GOP refresh but still same thing. The buy component also has a buy sourcing rule and ATP rules are all fine. Basically we are trying to find out why we see a from date of 3/14(in the resource availability below) . We are thinking that is when the component will be available after