Work Order Resource Transactions - Count Point / Charge Type Automatic - auto charges estimate

Summary:

When you plan a work order operation which is a count point / resource code where the charge type defaults to Automatic, it appears that when you complete the operation on the Review Maintenance Dispatch List, it automatically charges the full planned estimate for the resource (even if you have also manually charge hours)

For some reason I though the operation step also had to be "Automatically Transact" for this to happen.

Content (required):

Currently have the PMs setup with manual charge type (you could argue that PMs could be auto charge as repetitive),

But for corrective work orders it is a business process during planning to remember to update the default charge type from automatic to manual ( Still haven't found a way to default to manual). They are good, but processes fails in a dangerous state.