Withdrawn requisition that is for a project before approved release the commitment in projects
Summary:
A requisition was created for a project. It was withdrawn before it was approved. The funds status was not reserved.
However when the project manager ran the project costing the amounts still showed committed.
Is this expected?
I would have thought that nothing should be committed till approval is completed
Content (required):
Status - withdrawn
Funds status - Not reserved
Shows committed
Version (include the version you are using, if applicable):
Oracle Fusion Procurement