After Opting for HVGOP,system do not consider availability of Component items of ATO Item for ATP
Summary:
After Opting for HVGOP,system do not consider availability of Component items of ATO Item for ATP check
Content (required):
Hi All,
After we have opted for HVGOP, system doesnt look at availability of components and only considers lead time of the ATO Item.
As an example, we have an ATO Item which has a buy component under it with a lead time of 42 days(need to be purchased) and main ATO has lead time of 1 day defined on work definition. So before opting for HVGOP, system gave delay of 43 days in availability check for required date as current date.
0