GOP Scheduling Error
Summary:
Hi Experts,
We are seeing strange behaviour with GOP. We have a Allocation rules for some of the orgs. Although we see the Available Supply in Review Supply Availability and Review supply allocation but when submitting the order it gets into scheduling error. What could be the reason here if there is ATP supply available.
This is only happening for orgs which have allocation rules. GOP is scheduling other orders which don't have allocation rules properly.
Order management can't schedule the item because supply isn't available. (DOO-2685270) Details: If you set the Latest Acceptable Date, then order management attempts to schedule the item no later than the Latest Acceptable Date. Here are some corrections you can try. A. Set the Requested Ship Date so there is enough time to schedule, ship, and deliver the item. B. To make sure the item doesn't ship before Requested Ship Date and arrives no later than Latest Acceptable Date, set the Latest Acceptable Date so it provides enough time to schedule and ship the item. C. If you don't set