Is it possible to pass an indirect result to a gross-up (i.e. Process Separately) element?
Summary:
Is it possible to pass an indirect result to a gross-up (i.e. Process Separately) element?
Content (required):
We have an information element that we are using to collect hours / units data from self-service ICP transactions and then pass as indirect results to earnings elements for calculation of the final payment.
This is working perfectly apart from one gross-up element that is set to use the 'Process Separately' run type. The element should be processed separately but is appearing in the run results for the 'Regular' run with no pay value being calculated.
Can this be done or do indirect results only apply to the 'Regular' run?
0