Assigning activities which are about to be late.
Summary:
Understanding routing filter setting.
Content (required):
There is one setting "Assigning activities which are about to be late." in routing filter setting. Here I need to understand what does late means. Ideally it was in relation with service window or timeslot.
Those settings tell OFSC on how important it to be on time for the activities which are part of filter. On time means resource arrive within promised Service window or timeslot.
Now that in most part of the routing access schedule is taken into consideration whenever, there is no service window defined, could you please let us know if Access schedule is taken into consideration in case service window is not defined in a particular activity.