How to configure a maintenance program with resequenceable work definations ?

Received Response
11
Views
2
Comments
edited Nov 20, 2023 3:07PM in Maintenance 2 comments

Summary:

How to configure a maintenance program which has resequenceable operations on work definations ?

Content (please ensure you mask any confidential information):

Hi,

We have only one constraint

  1. There is one asset that needs to be follow up weekly, two weekly and monthly.

I have created work definations with resequence check box checked. Then I have created one work requirement for 3 work definations. The requirement setup as followed

Number of Intervals per Cycle is 4

If Work Definitions Are Concurrent: Suppress

Basis for Next Forecast Due Date: Calendar pattern

Calendar Pattern:Occurs every week on the following days: Monday

For weekly work defination due at cycle interval is 1