What if the client has a consignment agreement with a supplier for 10 days with aging point as Receipt. However, the supplier shipped and goods are delivered early than expected. Is there a functionality for system to calculate ownership transfer based on Requested date in PO rather than receipt date?
Content (please ensure you mask any confidential information):
Ex:
Requested date on PO = Dec 25th
Receipt date = Dec10th
Aging calculation/days = Receipt/10days
system to calculate 10 days from dec 25th and not from dec 10th