How to enforce GOP to provide SSD/Supply after 4 weeks of fixed delay?
Summary:Business expected SSD after 4 weeks from date of scheduling.
At Item level User defined Time fence set to 4 weeks (28 Days) at Master as well Shipping Organization level
ATP
1.Promise Mode set to Supply chain availability search
2. Infinite Availability Fence Definition = User Defined Lead time
User-Defined Fence in Days = 28
After data collection SSD on SO Line shows Customer request date + 1 day for the product having on hand or not having any onhand stock.
SO line products are Back-to-back enabled.
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
Oracle Fusion Cloud Applications24A (11.13.24.01.0)
0