What is the receipt inventory transaction that no affecting project actual cost

Summary:

Hi

We are implement project driven supply chain. We maintain our project number in one of chart of account segment. We have test some scenario between project and inventory:

  1. We create PR-PO-Good Receipt for specific project, with cost in item cost is 1000. When we run import cost, the project actual cost is 1000. We dont send the project number to the chart of account segment.
  2. We want to issue this item or material, but without affecting the project actual cost. So, we create movement request issue. The project actual cost still 1000. We send the project number to the chart of account segment.