View Pegging details for BLM recommended Planned Date
Summary:
We tested with one item one order line, no on-hand exist, GOP provided a SSD based on BOR lead times. We ran BLM for the same item same order line and BLM provided us different date. After we raised SR, we got to know for GOP and BLM the longest lead time subassembly are different. They have different way to look into it. GOP went into checking the availability of the components whereas BLM hit the ITF for the subassembly and went on to find the components details for another subassembly.
However the question is: Instead of raising SR, is there a way we can see the pegging details of BLM recommended dates the same way we could see the pegging details for GOP recommended dates?