How to consider the PO Promise Date in Supply Planning instead of Requested Delivery Date

Summary:

How to consider the PO Promise Date in Supply Planning instead of Requested Delivery Date

Example:

Initial PO Dates:

Requested Delivery Date (RDD) = 15-Nov-24

Promise Delivery Date (PDD) = 15-Nov-24.

Supplier Update PDD:

New Promise Delivery Date (PDD) = 01-Dec-24.

Now Supply Planning level we should be able to control which date to be considered for planning either RDD or PDD. How to set it up in current version 24C?