SCM: Restrict the PR Quantity to mentioned BOQ quantity
Dear Team,
Currently the user is maintaining BOQ manually, they wanted to upload the same into system against the project. and they wanted to have validations if the user submits the PR for quantity more than the BOQ quantity, system should restrict the user from submitting PR.
Kindly advise how we can achieve this.
For your information the Customer is not using Project and Inventory module, they are maintaining Project segments at GL level.
(You can consider that they are ready to implement required modules)
Regards
Prashant Kadlag
0