Manually Created Work Order
Attribute-Based Planning unconstrained supply plan
The scenario is as follows:
The user has manually created over 70 work orders without associating them with any project. The parent item has a proper item structure and work definition, and all the relevant data have been collected. However, the supply plan recommends canceling these work orders due to the absence of a linked project and no proper demand, which is expected behavior. The user, however, needs to drill down and inspect the child components. Since the plan recommends cancellation, this action is not possible. As a workaround, the suggestion was made to firm the work orders and re-run the collection and planning process.