While creating a Back to Back order a specific item the delay is showing as 699
Summary:
For a specific item which is back to back enabled when the check availability is done it show as delay of 699 days .
It is considering the days given in the profile "MSP_GOP_HORIZON_DAYS" (Set as 700).
Due to this the scheduled ship date in Sales order and Requested Delivery Date for the Transfer order created for this item is 26-Dec-2026 (2 years).
The Requested Delivery date in the transfer Order is not changing even though the scheduled ship date is changed to new date in the sales order.
Content (please ensure you mask any confidential information):
For a specific item which is back to back enabled when the check availability is done it show as delay of 699 days .
0