Summary:
I create a work order with a resource and assign 10 hours to it, then on the maintenance page I report 8 hours, then I change the status to completed and apart from the 8 hours reported, I load the original 10, how can I avoid this duplication?
then change operation status to complete
now I see 18 hours when I just neet to report 8