Managing Delayed WOs

Summary:

1 - How to prevent planning from suggesting new Planned Orders?

2 - How can the SO be notified when the pegged supply is delayed?

Content (please ensure you mask any confidential information):

Our customer have to requirements that I need help with:

1 - When the planner needs to delay a WO, how to prevent the system to create a planned order?

Because when we delay a Work Order and firm it, the system still creates a planned order to respect the "Request Ship Date" in the SO.

2 - How can the SO be notified when the pegged supply is delayed?