How to sequence two work orders in different production lines (resources)

Summary:

The last required component is produced in a work order/resource and the final product is produced in other work order/resource.

We need that the production of the final product starts "x minutes" after the component is done.

Content (please ensure you mask any confidential information):

Let's imagine this scenario:

Resource X - Component 99

Resource Y - Final Product

We need that planning suggests the start of the work order of the "Final Product", 1 hour after the completion of the "Component 99".

There is any way to achieve this?

Kind regards,

Pedro Silva

Version (include the version you are using, if applicable):