Project Cost & COGS & Revenue
Summary:
Dear All,
I have a scenario that I'm trying to get the focus on:
I'm buying material to a project/task. Perform manufacturing activities and ship off the assembly to a project sales order. My understanding of the financial transactions are:
Buying Inventory to Project (Debits Inventory Valuation) collected cost to projects 100AED use inventory project (50AED) and labor (50AED) and common stock (20AED) and complete/close the Work Order (Projects get another 70AED Cost) and inventory valuation debited another 70AED → 170AED Inventory Valuation and 170AED project cost
When I ship off the Sales Order Line for that assembly, Oracle will credit the inventory for (50AED 50AED 20AED) = 120AED and debit the project clearing account.