Hi Guys,
I have got a use case in which all the activities of one particular order should start one after the other in the same day. So I feel Linking them would help.
In the Linking templates, I am a bit confused about the Minimum and Maximum interval options such as Adjustable, Non-Adjustable and Unlimited as I am unable to understand what is the significance of Adjustable and Non- Adjustable field, when both these are asking for a corresponding Time Duration in minutes. According to my understanding, If I have to start an activity right after the previous one, the Minimum and Maximum interval should be 0 minutes and non-adjustable. But with this set up, I am unable to give Scheduling constraints as its throwing an error.