Can you please help me understand how a purchase requisition (PR) works in a maintenance work order?
I’m facing an issue: I raised a purchase requisition (PR) for operation sequence 10, but a purchase order (PO) was not created or received. However, I was still able to execute the work order.
Could you please explain the complete process of how purchase requisitions are handled in a maintenance work order?
From my understanding:
- A PR is created for an operation sequence with Destination Type set as Work Order.
- Then, a PO is expected to be created based on the PR.
- Once the PO is received, only then should the work order execution be allowed.
However, in my case, execution was allowed even though the PO was not received.