Warning in running demand plan
Hi all,
as described in the summary, running a replenishment plan with the "generate forecast" option (forecast shipment and/or forecast consumption), the "running demand plan" step returns me a warning.
The log of the scheduled process “Start Demand Planning Engine Manager” reports this to me: "Query for engine dates is not able to retrieve last forecast date. Engine can not proceed. Verify that plan horizon does not exceed maximum date loaded in time dimension table: select max(from_date) from MSC_DIMENSION_TIM_DYD where AGGR_TIM_LEVEL_ID = 52 Consider change in plan horizon days ..."
Could you help me understand it better ? What can I do to resolve this error ?