Can a resource work on several multi-day activities simultaneously?
Content
I have a requirement where resources usually work on several multi-day activities simultaneously, since the resources in this case are inspectors who supervise the work of labourers. The role of the inspector is to supervise the work of the labourers for a short while and then move to another place to supervise another activity while the labourers at the previous location continue their work. Is this possible in OFSC or do they absolutely have to end a multi-day segment in order to start working on another multi-day activity?
Thanks.
Version
Oracle Field Service Cloud 18A0