PO document is not considering ship date from planning
Summary:
Suppliers are shipping the material once a week for all one week demands and shipping calendars are defined. When planning releases those planned orders, it would have 5 different demand dates for current week and ship date would be same for these orders. But PO document lines are only displaying demand date in Requested delivery/Promised delivery date and not showing the ship date in the document which is present in planning.
Kindly help on how shipping date can be populated from planning to PO document. Due to this business see below concerns.
1. Purchase orders will have planned order due dates as Requested and Promised Delivery Date but it doesn't show the ship date in PO document which will cause confusion on when to ship these materials.