How are source org shipping calendar exceptions considered by GOP in back to back transfer flow
Summary:
There is a back to back enabled itemX configured to be fulfilled in the following manner - OrgB → OrgA → Customer
Global sourcing for item and customer = Transfer from OrgA
Local sourcing rule for item and OrgA = Transfer from OrgB
When an order is placed for itemX, order gets scheduled from warehouse OrgA and generates a supply order which creates transfer order from OrgB to OrgA
Other data:
There is no stock of ItemX available in OrgA
All Orgs have 5 day work week (Weekends not working)
ItemX processing days in OrgA = 2
ItemX processing days in OrgB = 9
OrgA timezone = CT
OrgB timezone = MT