HDL Load for Changing an Element Entry Value with an Effective Date in the Past
Summary:
HDL load for an element entry value change with an effective date in the past is erroring out.
Content (please ensure you mask any confidential information):
Hi Team,
An HDL load for an element entry value change with an effective date in the past is failing. This is a rare case I’ve encountered, but it is a valid scenario for our client, where a premium adjustment may be required due to updates in the Benefit Administrator’s system.
This update works fine through a front-end edit, but the HDL load fails with the following error message:
“Date-effective records can’t have gaps between the effective end date of one record and the effective start date of the next record.”