lead times not honored for reschedule suggestion?

Summary:

Hi Guru,

will system honor lead time for rescheduling PO? i have an item with total lead time for 108 days, but when system is not honoring the LT when it comes to PO reschedule suggestions, please kindly check below:

my calendar is 6 working days a week(from Mon to Sat)

obviously the date between suggested due date and suggested start date is way less than 108 days, and i also dont know how the compression days is calculated.

thanks in advance!


Content (please ensure you mask any confidential information):


Version (include the version you are using, if applicable):



Code Snippet (add any code snippets that support your topic, if applicable):

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!