Projected on hand and projected available balance calculations

edited May 6, 2026 9:39AM in Supply Chain Planning and Collaboration 3 comments

Summary:

Hi,

In Material Plan, How the calcualtions happens with Projected on Hand and Projected Available Balance. Can you pelase provide the formula as well.

Looks like the below formula are not matching to the content in screen shot

Projected On Hand = Previous Projected On Hand + Total Supply+Scheduled Receipts -Total Demand

PAB = Previous PAB+Total Supply+Scheduled Receipts+Planned Orders -Total Demand

In the below screen shot, If we see for 11-May-2026, We have scheduled receipts 11 consists of 10qty of PO with reschedule out action and 1 qty of In-transit shipment (Refer Screen shot-2)

In Total Supply it considerd only that Intransit shipment qty of 1