Transportation Schedule is not respected by GOP
Summary:
Hi,
The receiving days in Transportation schedule is not respected by GOP while scheduling the sales order.
Created a Facility schedule with Monday and Friday as working days.
Facility schedule is assigned to the customer/party.
While creating the order observed that the Scheduled Arrival Date is not falling on the customer receiving days.
User preference is "ET" (UTC-5).
Below is an example -
Receiving Days in Transportation Schedule is "Tuesday" and "Friday"-
Item
|
RAD of SO Line
|
SSD of SO Line UI
|
SSD of SO line in DB
|
SAD of SO line UI
|
SAD of SO line in DB |
|---|
0