Manufacturing WO Completed with Zero Cost - Rate-Based PO Not Included in Cost Rollup
Summary:
We are observing an issue with Mfg Work Order (WO) costing when using a rate-based Purchase Order (PO) for operation cost.
Scenario
- Created a Manufacturing Work Order with 1 operation
- No material items or additional resources were added to the WO
- A rate-based PO was created and associated with the operation
Expectation
- The system should consider the rate-based PO cost
- Cost should be rolled up to the WO
- mfg WO should be fully costed
- Appropriate cost accounting entries should be created
Actual Result
- After completing the Work Order:
- WO costing shows 0 cost
- Rate-based PO is not picked up to calculate total item cost