Project Performance Reporting OTBI ITD Actual Cost balances overstated
Summary:
Hi,
In Project Performance Reporting in the UI, the ITD Actual Cost balances are correct, however in my OTBI report the ITD Actuals balances are overstated. To test this I made a very simple OTBI (3 columns) and the ITD Actual Cost amounts were correct, so it seems as though something in my full report (15 columns) is causing the ITD Actual Costs to be increased or multiplied. My YTD Actual Costs are correct.
Thanks,
Brian
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
0