Hi All,
We would like to confirm whether it is possible to set up approval units in FCCS for specific years only, rather than from the beginning of the application.
Current setup:
- Application start year: FY23
- Approval unit configured for one scenario, starting from FY26
- Application is EOBP enabled
Issue:
The system does not allow us to lock FY26 unless all prior periods are locked first.
Question:
Is this a system limitation, or is there a way to achieve this requirement (i.e., managing approvals and locking from FY26 onward without having to lock FY23 to FY25)?
Any guidance or recommended workaround would be appreciated.