My customer is upgrading from PeopleSoft HRMS 8.0/PT 8.22 to PS HCM 9.1/PT 8.50. They are running MTP cycle 2 with a target go-live date of April 2011. With the new PT 8.51 release and the new features like testing etc. they are thinking of including PT 8.51 upgrade within their current ongoing upgrade project.
They need information around:
What is upgrade path for PT 8.51? Is there a direct path from PT 8.22?
What is an overall effort compared to their existing upgrade project? They are in MTP cycle 2 and want to know whether they can include PT 8.51 in next MTP? Or it needs to start from beginning to be on PT 8.51?
They need information around:
What is upgrade path for PT 8.51? Is there a direct path from PT 8.22?
What is an overall effort compared to their existing upgrade project? They are in MTP cycle 2 and want to know whether they can include PT 8.51 in next MTP? Or it needs to start from beginning to be on PT 8.51?