MPS & mrp
FG mps
SUB mrp
RAW mrp
MDS: FG's quantity as 20
(1)MPS advice as : 7 implenent as work order
6 implenent as PR
4 implement as PR
1 implement as PR
2 implement as PR
questions: why the plan aplit? in setting where?why there are PR?i think i have not the capacity planing.
(2)MRP advice as:
SUB--demand as 7(equal as advice the FG supply which MPS's advice as work order )
3 implement as work order
1 implement as PR
3 implement as PR
question:why the plan aplit?why there are PR?why the demand cannot based on MDS.