Default Process Scheduler when submitted process scheduler is not selected.
We have three process schedulers running, PSNT, PSUNX, PSUNX2, each with a maximum of 3 concurrent process per process type. So at most, 3 of any process type (SQR Report, AppEngine, etc.). The PSUNX process scheduler is designated as the master (Server List Tab Master = 'Y'.
Last night, running month-end reporting we had 3 SQR Report processes running in the PSNT process scheduler, and a number (20) of PO SQR Report process, POPO005.SQRqueued up. The POPO005.SQR processes were submitted with no server selected in the process definition.