Upgrade HCM 9.1 to 9.2 - Questions on Change Assistant Congifuration !
Hello Everyone
I need expert openion and solution on the HR 9.1 to HR 9.2 Upgrade process of configuring the Change Assistant.
My source and target & Copy of current demo databases are on the same server and the Change Assitant is also on the same server. In other words on a single windows host computer.
So when I configure the Change Assistant I have the following General, Source Database environment, Target Database environment and Copy of Current Demo Database environment.
This is the INIT Pass of the upgrade.
Environment details:
Source :
PT 8.553.10 /w HCM 9.2 - Demo Database
SQL Server 2012
Windows Server 2008 R2 (64-bit)