HCM Upgrade 9.1 to 9.2 - Task 5-10-3: Performing Data Conversion Concurrently
We are in our Initial Pass for upgrade of 9.1/8.5.1. to 9.2/8.5.3.12. When running Change Assistant job step Performing Data Conversion Concurrently (using process scheduler) is failing. The step appears to complete 3 processes successfully then fails. Initially message showed that CA could not reach location of process scheduler logs. Process logs show message: Information: Process 302810 completed, but Change Assistant is unable to retrieve the log file from "z:\hr920\appserv\prcs\hr92s\log_output" (this is the mapped path on the Change Assistant workstation).
We tried switching CA Method of retrieving Process Scheduler logs setting to File Copy and then to None but both return same error.