How can I measure EV ?
Hi,
How can I measure EV based on weighted top down estimation (units) having also resource allocation to the project .
I want to measure differently EV and allocation of resources and cost. Not all the activities have a cost value, so the EV based on cost is not convenient.
Budgeted units from top down estimation will mix with the budgeted units from resource assignment.
Please advice.
Thx,
Alex