Combining PeopleTools Upgrade and Application Update Jobs?
Hi,
We are currently running an Tools Upgrade and Application Update activity that involves following steps,
1. Perform PeopleTools Upgrade from 8.54.07 to 8.55.07
2. Perform Application Update from HCM 9.2.011 to HCM 9.2.017
We have started this activity and have so far completed following steps,
- Installed and configured HCM 9.2.017 - Native OS Image, delivered on PT 8.55.03
- Patched PeopleTools to PT 8.55.07
- Completed Initial pass of PT Upgrade to Copy of Prod environment from 8.54.07 to 8.55.07
Our next steps,
- Create a new change package for applying application updates - delta between 9.2.017 & 9.2.011
- Apply application update via this CA job
Can you please clarify on below items,
1. Is it possible to merge the 2 jobs mentioned above? PT upgrade and application update change jobs.