Revaluation not generating journals for some of the process group in run control
Hi,
Has anyone encountered scenario in PUM 22 wherein multiple revals running in parallel (e.g 12 revals concurrent) causing some revals not to generate journals for some of the process groups (although it's expected to generate). But if the reval is run on its own (with no other concurrent process), it generates the journals completely.
To illustrate for one reval run control with 4 process groups defined:
RUN1: Run with 12 concurrent reval processes running
1st process group - generates journal
2nd process group - generates journal
3rd process group - did not generate journal (supposed to generate)
4th process group - did not generate journal (supposed to generate)