Functional Testing for upgrading from PeopleTools 8.55.12 to 8.55.23

edited Oct 18, 2018 5:00AM in PeopleTools and Lifecycle Management - PSFT (MOSC) 6 commentsAnswered

Hi All,

We are on PeopleTools 8.22.12 (PeopleSoft 9.2) and we have the following modules-

Accounts Payable, Contracts, Accounts Receivable, Project Costing, Asset Management.

There is a plan to upgrade the PeopleTools to 8.55.23. This being a minor upgrade, I would like to know the kind of functional testing required for this project. Will testing critical day to day business processes be sufficient ? We are testing for DB upgrade and the plan is to combine the testing for the PeopleTools Upgrade with it. For DB upgrade( minor ), we are testing only the critical processes( checking performance).

Thanks,

Debolina

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center