9.2 PeopleSoft ADS
I am hoping someone can point to what am doing wrong here
1) Created Data Set - Test for Profile Management (Essentially, trying to migrate a new effective dated row for PERSON type profile)
2) Ensured I got parent and 6 child records
3) Saved Data Set
4) Now, created test project via data migration bench (using right effective date)
5) Chose the test dataset, checked for integrity (no errors, says, validated)
6) However, when I exported results to pdf file, it only shows two (2) records. Project Navigator shows only one record. Clicking on the record does nothing
What am I doing wrong?