BCWS is greater than BAC in Earned Value Calculations - Primavera

edited Sep 8, 2020 5:04AM in Primavera (MOSC) 1 commentAnswered

have two files for a project that I am using in classes.  I have a problem understanding how the calculations are done.  Here are the characteristics of the project:

The baseline is a progressed schedule (Rebase)
Actual Cost is not reported in the schedule (AC = 0)

I found that some activities have its Planned Value Cost (BCWS) is greater than the Budget at completion (BAC)
I found that some activities have its Planned Value Cost (BCWS) and the Budget at completion (BAC) changed from the values that were shown in the Rebased and Updated Schedules. They were mostly similar to the Remaining Cost but not always.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center