Dunning By level - First letter to generate 15 Days after due date
Hi,
We have setup dunning by Level, - Level 01 Interval is Zero. So First letter generate on Next day of the due date. Now And Level 02 interval 30 - second letter generate on 30th day from first letter. Etc.
Now, we have requirement to change setup- First letter to generate on 15 days after due date. If we change the interval from 0 to 15 on Level 01, it is not working as expected. Please share your thoughts on this.
Thanks