How does Oracle setup WIP Job's start date
Hello,
I have a question please, I'm using Oracle R12 (12.1.3), and I created 4 Sales Orders like below——
S0001 Order Date is 2021-Nov-10th, Request Date is 2022-Mar-16th, Order Qty is 100
S0002 Order Date is 2021-Nov-16th, Request Date is 2021-Nov-16th, Order Qty is 20
S0003 Order Date is 2021-Nov-17th, Request Date is 2021-Dec-13th, Order Qty is 100
S0004 Order Date is 2021-Nov-25th, Request Date is 2021-Dec-16th, Order Qty is 100
Then MRP released above demands and generated 3 related WIP Work Orders:
W0001 Release Date is 2021-Nov-10th, Qty is 100, Start Date is 2022-Mar-14th, and Completion Date is 2022-Mar-16th