Final Approval of IGT Order by the Requesting Agency ==> from within the EBS
We are still testing this functionality of IGT Orders. As of now the process seems to be:
- Requesting Agency pre-approves the IGT Order in EBS (Purchasing).
- Pushes the pre-approved IGT Order to G-Invoicing portal.
- Servicing Agency approves the IGT Order (either in G-Invoicing portal or in EBS Projects).
- Requesting Agency has to approve the IGT Order in G-Invoicing Portal again for the IGT Order to get a status of 'Open'.
- IGT Order is pulled into EBS Purchasing as 'Approved'.
Why should the Requesting agency login to G-Invoicing Portal again to approve the IGT Order in step#4 above? They have already approved the IGT Order in step#1 in EBS Purchasing.