Oracle RMS - V19.3 - Component Cost on Vendor Pack POs
Hi Team,
As per the Oracle process the component cost at the time of PO receipt is calculated based on the latest percent contribution of ext comp cost on item at item supplier country level to the cost on PO for the Prepack.
Is there any option in oracle too have percent contribution for the components to be captured at the po level when writing the pos for vendor packs, so that its not differing if the cost on component item gets changed at the item supplier level.
This creates problem when cost changes are done on components after the pos are written. PO receipt cost for the components changes everytime the component cost is changed at item level.